7 options to solve Welney flooding and one could cost £58m
From last winter at Welney when drivers decide whether to risk crossing the flooded Washes or to take a diversion. - Credit: Terry Harris
Cost of resolving flooding on the A1101 at Welney could be up to £58m, says Norfolk County Council.
“Potential schemes have been considered over the last 30 years but not progressed due to cost and complexity,” says a report to its cabinet members.
Although £58 is the highest estimate for one of the seven options being considered, it could be as low as £4m.
It will depend, says the report, on the preferred option “and desired level of resilience”.
Whichever option eventually succeeds, the county council says although it could contribute some funds towards it “government support will be essential”.
The report says the A road crossing the Ouse Washes – part of a flood defence system and a Site of Special Scientific Interest – regularly floods.
This results in “closure of the road and a 20-mile diversion for up to a third of a year”.
Most Read
- 1 Person hit by train between Manea and Peterborough
- 2 First visit not 'a flying success' but pub deserves second chance
- 3 Sanctuary Housing criticised over empty homes in Ely
- 4 Fire crews called to car fire on railway line
- 5 MP officially begins new era for major UK supplier
- 6 Huntingdon and Peterborough hospitals bring back masks after rise in Covid numbers
- 7 Lorna’s successful plea to remove £3 shower charge for disabled visitors to The Hive
- 8 Hunt is on for arsonists after 5am car fire
- 9 Threat to cancel or 'indefinitely pause' £450m Ely rail upgrade
- 10 'Cuckooing' drug dealer caught with cocaine to the value of £3,670
In May the latest meeting with MP Liz Truss (she first attended a ‘floods summit’ with NE Cambs MP Steve Barclay seven years ago) “discussed findings of an updated feasibility study".
It was agreed to look at preferred options, balancing the cost, deliverability and environmental factors.
And to “develop costs in more detail and indicative delivery timescale, identifying and agreeing funding”.