‘Significant risks’ add to final bill for Ely Southern Bypass, county councillors warned
Ely bypass new progress photo:While steel is being placed on the centre V-pier (foreground), the west V pier is getting filled with concrete (background). Both will support the new viaduct over the River Great Ouse. - Credit: Archant
Some major issues have been identified with construction of the Ely Southern Bypass that could add “significant” costs to the final bill.
A report to county councillors points out that “whilst work is progressing on site, some significant risks have emerged requiring additional work”.
These include Network Rail requirements, the diversion of statutory undertakers’ plant, buildability issues arising from the complex V piers and additional temporary works resulting from poor and variable ground conditions.
The report says: “These will increase the outturn cost of the scheme significantly and are currently being considered with the contractor to minimise the impact on the project and to reduce the cost impact.”
Completion date is likely to be late summer/autumn 2018 depending on weather.
The county council says it is working with the contractor to identify options to mitigate against delay and minimise costs.
“A number of value engineering opportunities are also being explored,” notes the report.
Most Read
- 1 Woman, 80, dies following A141 crash
- 2 Pair trapped after A142 crash rescued from ditch
- 3 'Rubberneckers' cause second crash trying to view overturned lorry
- 4 Village farm buildings targeted in arson attack
- 5 Have you seen Harry Gibson? He's wanted by police
- 6 Chapel conversion withdrawn following stinging rebuke
- 7 Councillors left disappointed as decision made on £37m station project
- 8 Both drivers seriously injured after head on crash
- 9 Two women fighting for life after A141 crash
- 10 Ely and Cambridge for Neil Hilgrove Colledge recitals
The Cambridgeshire and Peterborough Local Enterprise Partnership (LEP) committed £22 million to the project with the remaining funds split between the county council (£8 million), district council (£1 million) and Network Rail (£5 million).
Work began on site last March
VolkerFitzpatrick was appointed in summer 2016 to build it.