Town bridge to close for 10 weeks as £350,000 flood defence improvements get under way in Wisbech

12:30 14 February 2014

South Brink Wisbech, Water flooding onto road from river.

South Brink Wisbech, Water flooding onto road from river.

Archant

More work to protect Wisbech from flooding is to begin on February 24 as the latest phase of improvements get under way.

The latest work, costing around £350,000, is designed to maintain the retaining wall flood defence on South Brink, Nene Quay.

At the same time Cambridgeshire County Council will complete bridge repairs on the Town Bridge, carry out local highway improvements and road resurfacing.

A council spokesman said: “To enable work to be completed as quickly as possible, the Town Bridge will be closed to traffic and pedestrians for 10 weeks from March 3. “Signed diversions for walkers and drivers will be in place.”

Millions has been spent on flood defence work in Wisbech in recent years including upgrading of the retaining wall at Freedom Bridge.

The town is said to have a 1 in 200 year chance of major flooding and in recent years a considerable amount of floodwall reconstruction has been undertaken.

In 2010 work finished on a £12million Environment Agency flood prevention scheme and won the main contractors a national award.

The work entailed flood defences along four kilometres of river bank and used some 330,000 bricks with work carried out along both the South Brink and North Brink.

1 comment

  • So, the Fair is here from 1-8 March, and the town bridge is closing for 10 weeks from 3rd March. Brilliant timing by the Council as usual!

    Report this comment

    Norfolk and Good

    Sunday, February 16, 2014

Yesterday, 16:44
Stephen Talbot

A former Cambridgeshire police chaplain has been has been jailed for possession of indecent images of children.

Yesterday, 12:21
Left: Tim Wildbore and Andrew Thornewell.

Inquests have been opened into the deaths of two men who suffered fatal injuries in a crash on the A10.

Yesterday, 08:20
Witchford Village College head teacher, Chris Terry

Pupil progress at Witchford Village College is “not good enough” in some subjects and the school requires improvement, according to Government inspectors.

Yesterday, 15:40
Cambs Election 2015 logo

The general election in May looks set to be a two horse race in this area according to a new poll produced this week on how people will vote on May 7.

Most read stories

Most commented stories

Digital Edition

Image
Read the Ely Standard e-edition today E-edition